Lessons learnt from bike path cost overrun

CYCLING

23 November 2018
 

West Sussex County Council says it has learnt lessons from the construction of a path on the National Cycle Network that more than doubled in cost.

Consultant CH2M reported in December 2014 that the estimated design and construction cost of the three-mile Littlehampton to Bognor Regis section of National Cycle Network route 2  was £900,000, which included a 10 per cent risk factor on construction costs and a 25 per cent adjustment for optimism bias. 

The council made a...

+77% more

 

Electric Vehicle Project Officer
London Borough of Hounslow
Heart of Hounslow, 92 Bath Rd, Hounslow TW3 3EL
£45,750 – 49,056 (Career Graded)
Principal Highways and Transport Planning Officer
West Northamptonshire Council
Northampton
£49,587 - £52,860
Assistant Director of Regulatory Services
Derbyshire County Council
County Hall, Matlock/Hybrid
Grade 16 £71,202 - £77,495 per annum
View all Vacancies
 
Search
 
 
 

TransportXtra is part of Landor LINKS

© 2026 TransportXtra | Landor LINKS Ltd | All Rights Reserved

Subscriptions, Magazines & Online Access Enquires
[Frequently Asked Questions]
Email: subs.ltt@landor.co.uk | Tel: +44 (0) 20 7091 7959

Shop & Accounts Enquires
Email: accounts@landor.co.uk | Tel: +44 (0) 20 7091 7855

Advertising Sales & Recruitment Enquires
Email: daniel@landor.co.uk | Tel: +44 (0) 20 7091 7861

Events & Conference Enquires
Email: conferences@landor.co.uk | Tel: +44 (0) 20 7091 7865

Press Releases & Editorial Enquires
Email: info@transportxtra.com | Tel: +44 (0) 20 7091 7875

Privacy Policy | Terms and Conditions | Advertise

Web design london by Brainiac Media 2020