Uncertain timetable for Transpennine electrics

17 December 2014
 

Delivery of Transpennine rail electrification between Manchester, Leeds and York may have slipped by almost two years, Network Rail documents suggest. 

NR’s Control Period 5 enhancements delivery plan published in September gives a December 2018 completion date for a project called ‘North programme Yorkshire including Transpennine electrification’.  

A November update of NR’s major schemes shows, however, a completion date for the £440m project of July...

+75% more

 

PDP Transport Planner and Modeller
Surrey County Council
Victoria Gate, Woking, GU21 6JD
£33,552 to £45,135 per annum
Principal Highways Development Officer
Cheshire East Council
Crewe
£41,771 - £48,072 per annum
Transport & Development Planners (2 x Full Time, 1 x Part Time)
Kent County Council
Highways Offices including Ashford, Aylesford & Maidstone (Home/ Flexible Working)
£30,404 - £38,304 per annum
View all Vacancies
 
Search
 
 
 

TransportXtra is part of Landor LINKS

© 2026 TransportXtra | Landor LINKS Ltd | All Rights Reserved

Subscriptions, Magazines & Online Access Enquires
[Frequently Asked Questions]
Email: subs.ltt@landor.co.uk | Tel: +44 (0) 20 7091 7959

Shop & Accounts Enquires
Email: accounts@landor.co.uk | Tel: +44 (0) 20 7091 7855

Advertising Sales & Recruitment Enquires
Email: daniel@landor.co.uk | Tel: +44 (0) 20 7091 7861

Events & Conference Enquires
Email: conferences@landor.co.uk | Tel: +44 (0) 20 7091 7865

Press Releases & Editorial Enquires
Email: info@transportxtra.com | Tel: +44 (0) 20 7091 7875

Privacy Policy | Terms and Conditions | Advertise

Web design london by Brainiac Media 2020